Use it yourself
Each kWh used on site avoids buying one kWh at the applicable retail tariff, which is generally worth more than the export tariff.
You can sell surplus electricity after meeting the eligibility requirements, applying to the Solar for People programme, and completing the approved grid connection. The main principle is to generate for self-consumption first and sell only the surplus.
Yes. An eligible residential customer must apply, be approved, sign the contract, install compliant equipment, and pass the connection inspection. The B.E. 2569 (2026) programme pays 2.20 baht/kWh for 10 years and allows an export offer of no more than 5 kW AC per applicant.
This information refers to the announcements and PEA system published in B.E. 2569 (2026). Conditions, quotas and procedures are changeable. You should check the agency's website again before investing.

| Applicant | Eligible residential electricity customers under the relevant utility's conditions |
|---|---|
| Format | Generate primarily for self-consumption and sell the surplus |
| Offering quantity | No more than 5 kW AC per applicant |
| Purchase price | 2.20 baht per kWh |
| Contract term | 10 years |
| Combined procurement target | Not more than 500 MW AC shared in PEA and MEA areas. |
| Commercial operation deadline | SCOD within B.E. 2570 (2027), subject to the programme conditions |
See the original announcement at Office of the Energy Regulatory Commission and details for applying for a PEA area at PPIM system
During the day, the home uses solar electricity as it is generated. Any permitted surplus can flow to the grid. At night, the panels do not generate electricity, so the home continues to buy electricity from the utility as usual.
Each kWh used on site avoids buying one kWh at the applicable retail tariff, which is generally worth more than the export tariff.
The remaining electricity is therefore sold at the rate of 2.20 baht per unit according to the contract of the project year B.E. 2569 (2026).
Your first goal should be to reduce your electricity bill by using it yourself. Then look at the income from excess electricity as an additional benefit.
For PEA areas, the application page asks for a current electricity bill, preferably no more than three months old, and states that applications are handled on a first-come, first-served basis.
Create an account in the utility's application system, enter the supply-point details, and upload all required documents.
The utility reviews the documents and technical capacity, then publishes the approved applicants.
Approved applicants pay the required fees, submit the documents, and sign the contract by the deadline.
Install the approved design using compliant equipment, then apply for grid connection.
Proceed with notification of energy business operations that are exempt according to the ERC's procedures.
The utility inspects the system, replaces the meter where required, tests the connection, and approves commercial operation.
PEA's B.E. 2569 (2026) application page lists a connection-inspection fee of 2,000 baht before VAT, or 2,140 baht including VAT. Confirm the actual charges for the relevant area and application.
100 kWh × 2.20 baht/kWh = approximately 220 baht per month or 2,640 baht per year if there is electricity remaining at the same level every month This example does not deduct accounting conditions, taxes or other expenses as the case may be.
Therefore, it can be seen that designing a system to use the electricity itself appropriately is often more important than installing a large system just to sell electricity.
Do not assume an existing installation will qualify: its equipment, design, and capacity must match the programme requirements and application. Check eligibility and procedure before ordering equipment.
The B.E. 2569 (2026) programme does not prohibit a BESS, but its installation and operation must comply with the engineering standards of the contracting utility.
Bangkok, Nonthaburi, and Samut Prakan are in the MEA area. Other provinces are generally in the PEA area. You should check the request receiving system of the agency specified in the electricity bill.
Send the electricity bill to the PTH GREEN team to check the basic information and design it for your own use in a worthwhile manner before submitting a request.